T 2000 is a portable current transformer test set which allows to perform many different measurements such as saturation, ratio and polarity tests and CT winding resistance test. Substation maintenance and commissioning test equipment, T 2000 is extremely appreciated by electrical engineers for its high accuracy and portability.
Datasheet
|
T 3000 is a primary current injection testing system designed to perform primary tests requested in substations commissioning. It allows to perform different tests and measurements on current transformers, voltage transformers, power transformers, protection relays, energy meters and transducers
Datasheet |
BU 2000/4000 is an option for primary current injection and transformer test equipment T 3000 and T 2000. This complementary module is an innovative design concept that allows to avoid the power losses due to long cables connections
eKAM is the new fully automatic electronic primary injection test equipment. e KAM test system includes two portable units: one control unit with a large graphical display, that adjusts the output, and one current unit (up to 2000, 3000, 5000A). It can also perform Step and Touch tests and ground resistance tests.
Datasheet
|
iCT1 - CT/VT Test Set is the NEW and most advanced portable equipment capable to test current, voltage and combined transformers. With the low voltage method, known as "DC method", iCT1 is able to test Current Transformers with a very high saturation voltage, up to 30 kV, in a complete safety mode. Quick and easy to use tool, iCT1 allows to perform tests in one shot without changing the connection to the CT, thanks to the integrated 5-TAP Switchbox.
Datasheet
|
- Control STS and TD remotely from PC
- Create test plan
- Download stored test results via Ethernet cable
- Create and customize test reports
- Print test results
Datasheet
|
STS 4000 is a multifunction substation maintenance & commissioning test system for current, voltage and power transformers, designed to perform primary tests requested in substations commissioning. It allows to perform accurate tests on CTs, VTs, PTs and ground grid.
Datasheet |
STS 5000 is a multifunction substation maintenance & commissioning test system for current, voltage and power transformers designed to perform primary tests requested in substations commissioning. It allows to perform accurate tests on CTs, VTs, PTs and ground grid.
Datasheet |
This substation testing device is designed to grant high current output when needed in substation commissioning activities.
Datasheet
|
Instrument Transformer Testing (CT / VT Testing)
Instrument transformer testing involves verification, calibration and functional testing of current transformers (CT) and voltage or potential transformers (VT/PT) in power networks. Test instruments supply defined currents and voltages to verify transformation ratio, accuracy, phase shift, insulation strength, load behaviour and overall functionality under operating conditions.
FAQ
What is instrument transformer testing?
It is the procedure for testing current and voltage transformers (CT/VT/PT) to verify their transformation accuracy, phase relationship, insulation integrity and operational reliability.
Why is testing of transformers necessary?
Transformers provide critical measurements for metering and protection. Faulty or inaccurate transformers can lead to incorrect measurements, misoperation of protection systems or network instability. Regular testing ensures safety and accuracy.
Which transformer types are tested?
Current transformers (CT), voltage/potential transformers (VT/PT), combined measurement and protection transformers and transformer assemblies in switchgear or distribution systems.
Which parameters are measured during testing?
Transformation ratio, accuracy (ratio & phase), leakage current, load response, insulation resistance, open-/short-circuit behaviour, thermal performance, and, if applicable, secondary outputs under load or fault conditions.
What does a typical test sequence look like?
Visual inspection and identification, connection to test set, injection of defined primary current/voltage, measurement of secondary outputs, comparison with nominal values, phase-shift and error analysis, insulation test, load and short-circuit tests, documentation.
Why are ratio and phase angle important?
Ratio ensures correct scaling of primary to secondary values; phase angle must be accurate to maintain proper synchronization for protection and measurement systems — crucial for three-phase grids and protection coordination.
How is insulation strength tested?
By applying a defined test voltage between primary, secondary and earth to check insulation integrity, shielding and isolation between windings and grounded parts — preventing breakdown or faults.
How are results evaluated?
Measured values are compared with manufacturer specs or standards. Deviations beyond tolerance — ratio error, phase shift, insulation failure — indicate rejection or need for repair.
How often should instrument transformers be tested?
Recommended at commissioning, after maintenance or repairs, after modifications, after major events (faults, overloads) or at periodic intervals per regulation or grid operator policy.
Who should perform these tests?
Qualified electrical engineers or protection & metering technicians experienced in medium/high-voltage systems, CT/VT testing and safety procedures.
Which test equipment is used?
Multi-channel test sets with high current/voltage sources, measurement modules, load simulation capability, insulation test modules, software-based control and documentation tools.
What is the difference between primary and secondary testing?
Primary test injects current/voltage through the actual primary circuit (real load); secondary test applies signals directly to transformer secondary terminals or relay inputs — useful during maintenance without disrupting supply.
When is secondary testing appropriate?
When the primary circuit cannot be de-energized or taken offline — allows verification of ratio, phase, insulation and relay-side behaviour without interrupting operation.
Which documentation is required?
Test reports with transformer data (type, ratio), test conditions (current/voltage, load), measured values, tolerances, date, tester and verdict. This ensures traceability and reference for future inspections.
Does temperature affect test results?
Yes — temperature influences winding resistance and insulation properties. Tests should be done under defined conditions or with temperature recorded for later evaluation.
What to do if deviations are detected?
Disassemble the transformer, inspect windings and insulation, perform maintenance or replacement, then repeat tests to verify compliance before reconnection.
Which standards and safety procedures apply?
Standards for medium/high-voltage testing, insulation testing, earthing, isolation and operational safety must be followed. Tests must be done by trained personnel under safe, defined conditions.












































































































































































Datasheet
Datasheet